Date Topic Details Pictures
26/1/2007 也蒙思源小學第二期工程記錄進度報告 Yamong Xiyuan School Phase II Progress Report 07-01-25 1/4 因貴州地區天雨關係,令由達地鄉至也蒙地區村級公路變成泥濘路,阻礙運輸建築材料。 也蒙地區各村村民積極協助修補公路。 The heavy rains at Guizhou turned the local village roads between Dateixian and Yamong area into muddy ground, causing delay in transportation of building materials. All Yamong villagers assisted vigorously to repair the roads.
26/1/2007 也蒙思源小學第二期工程記錄進度報告 Yamong Xiyuan School Phase II Progress Report 07-01-25 2/4 因天雨關係,整個建校工程進度稍作延緩。建校領導小組己作出相應措施補救。 Due to heavy rains, the construction project was slightly delayed. The project team has taken recovery measures.
26/1/2007 也蒙思源小學第二期工程記錄進度報告 Yamong Xiyuan School Phase II Progress Report 07-01-25 3/4 因貴州達地鄉山區進入冬季天雨和霜冬期,嚴重影響建築工程的進度。 寒冷天氧亦造成電線、電話線結冰和斷裂,令供電系統和通訊終斷,有關部門正全力搶修。 The heavy rain and snow season has adversely affected the construction progress. The local power and communication networks have been suspended and the authorities are taking recovery action with full strength.
26/1/2007 也蒙思源小學第二期工程記錄進度報告 Yamong Xiyuan School Phase II Progress Report 07-01-25 4/4 因貴州達地鄉山區進入冬季天雨和霜冬期,嚴重影響建築工程的進度。 寒冷天氧亦造成電線、電話線結冰和斷裂,令供電系統和通訊終斷,有關部門正全力搶修。 The heavy rain and snow period has adversely affected the construction progress. The local power and communication networks have been suspended and the authorities are taking recovery action with full strength.
11/12/2006 也蒙思源小學第二期工程記錄進度報告 Yamong Xiyuan School Phase II Progress Report 06-12-11 1/3 因公路橋被重型貨車壓斷,建校舍工程延後約10天,現已回復正常運材料。預計整個工程將在春節前完工。 The heavy-weight trucks have caused the collapse of the motorway bridge leading to a delay of about 10 days in the school building project. Materials delivery has resumed and the entire project will be expected to be complete before the Spring Festival
11/12/2006 也蒙思源小學第二期工程記錄進度報告 Yamong Xiyuan School Phase II Progress Report 06-12-11 2/3 因公路橋被重型貨車壓斷,建校舍工程延後約10天,現已回復正常運材料。預計整個工程將在春節前完工。 The heavy-weight trucks have caused the collapse of the motorway bridge leading to a delay of about 10 days in the school building project. Materials delivery has resumed and the entire project will be expected to be complete before the Spring Festival
11/12/2006 也蒙思源小學第二期工程記錄進度報告 Yamong Xiyuan School Phase II Progress Report 06-12-11 3/3 因公路橋被重型貨車壓斷,建校舍工程延後約10天,現已回復正常運材料。預計整個工程將在春節前完工。 The heavy-weight trucks have caused the collapse of the motorway bridge leading to a delay of about 10 days in the school building project. Materials delivery has resumed and the entire project will be expected to be complete before the Spring Festival
4/9/2006 原也蒙完全小學現時狀況之一 Status 1 of former Yamong School 原也蒙完全小學校舍球場 Sport ground
4/9/2006 原也蒙完全小學現時狀況之二 Status 2 of former Yamong School 破舊洗手間 Worn-out washroom
4/9/2006 原也蒙完全小學現時狀況之三 Status 3 of former Yamong School 原也蒙完全小學廚房 Kitchen
4/9/2006 原也蒙完全小學現時狀況之四 Status 4 of former Yamong School 煮食情況 Cooking conditions
4/9/2006 原也蒙完全小學現時狀況之五 Status 5 of former Yamong School 課室環境 Classroom conditions
4/9/2006 原也蒙完全小學現時狀況之六 Status 6 of former Yamong School 用鐮刀削鉛筆 Sickle as pencil sharpener
4/9/2006 原也蒙完全小學現時狀況之七 Status 7 of former Yamong School 女學生宿舍 Female student's dormitory
4/9/2006 原也蒙完全小學現時狀況之八 Status 8 of former Yamong School 課室 Classroom
1/9/2006 也蒙思源小學規劃圖 Yamong Xiyuan School 1/3 2006-09 也蒙思源小學新教學樓整體設計規劃圖 Design plan of new classroom building. 1/3
1/9/2006 也蒙思源小學規劃圖 Yamong Xiyuan School 2/3 2006-09 也蒙思源小學新教學樓整體設計規劃圖 Design plan of new classroom building. 2/3
1/9/2006 也蒙思源小學規劃圖 Yamong Xiyuan School 3/3 2006-09 也蒙思源小學新教學樓整體設計規劃圖 Design plan of new classroom building. 3/3
1/9/2006 2006-09-1日刊登貴州政協報內資料 News clip appearing in Guizhou PCC Newspaper on 1.9.2006 介紹本基金與雷山政協、雷山教育局簽訂援建也蒙思源小學計劃。 Article regarding the signing of agreement between CCEF, the Leishan Political Consultative Conference & the Leishan Bureau of Education, for subsidy of the Yamong Xiyuan School project.
1/8/2006 貴州省偏遠山區學校工作計劃 Work plan for school at Guizhou Province remote mountainous area 本基金與香港思源基金會携手合作援建貴州省偏遠山區學校工作計劃。 有關援建黔東南州雷山縣達地水族鄉《也蒙小學》第一期地基工程,已於本年七月底破土動工,整項工程約需110天工程期完成,新校舍及配套設施將在十一月交付使用。建校領導小組並計劃新校舍竣工典禮,將安排在十一月十五日至十九日苗年期間舉行。該項建校工程由凱里東信建築工程公司中標承建。 CCEF and HK Xiyuan Foundation jointly sponsored the construction of Qiandongnan Datei Suixiang Yamong Xiyuan School. Phase I site foundation work commenced in July 2006 and the whole project, undertaken by Hoili Dongshun Construction Co., was estimated to last for 110 days. The school building and related facilities will be ready for operation by November. Opening ceremony is set for Miao New Year during 15-19 November.
14/6/2006 搶修公路 Urgent repair of motorway 在6月14日和7月16日期間,貴州雷山縣天氣惡劣,連續數天下滂沱大雨,數個地區造成山泥傾瀉和泥石流,埋沒了一段雷山縣往達地水族鄉也蒙村的公路,山泥傾瀉量約三千立方泥土。建校領導小組發動一批鄉民力量,並借用一部挖泥機配合搶修公路,搶修工作已於2/08日全面完成,公路現已回復通車,令建校工程隊的運輸材料工作得以順進行。 During the period from 14 June to 16 July, a section of motorway connecting Leishan and Yamong village was blocked by landslide due to heavy rains. The project team borrowed a bulldozer and enlisted assistance from the villagers to repair the motorway. Materials delivery resumed on 2 August upon completion of road repair.